Case Study
AHF Retrofit
Client
Commerzbank
Product
A2 Filter Modules
Sector
Banking
Smart AHF Retrofit Replaces Failing Equipment at Commerzbank
Summary
With 10 legacy AHF units failing, Power Capacitors delivered compact replacements that didn’t need
wall-mounting—restoring power quality and BMS compatibility.
Client Background
Commerzbank via facilities contractor.
Problem
Existing provider couldn’t supply replacements. Wall-mounted units were unsuitable due to space
constraints.
Solution
We supplied Merus AHFs that fit into existing footprints. We also coordinated with the BMS contractor to
ensure full software compatibility.
Results
-
Space-efficient AHF solution
-
Complete BMS integration
-
All 10 units replaced with minimal disruption
Testimonial
“Power Capacitors gave us exactly what we needed—no fuss, no compromise. A brilliant upgrade from start
to finish.” – Facilities Manager
Need to replace failing AHFs in a tight space? Let’s design a smart retrofit that fits your needs.
“We always use Power Capacitors Ltd. Nothing
is ever too much trouble, and the quality is second
to none!”
Operations Manager
AF Switchgear