Case Study
Increased Production Capacity
Client
ROM
Product
PFC Refurbishment
Sector
Site Services
How Site Services Transformed ROM Witham’s Production Capacity
Summary
With limited electricity demand availability, ROM Witham couldn’t scale production. Our site services
improved load efficiency and restored Power Factor control, unlocking 33% more capacity.
Client Background
ROM Ltd, a supplier of steel reinforcement products for construction.
Problem
A power factor of ~0.75 lagging was inflating their kVA usage, restricting expansion.
Solution
We refurbished their PFC system onsite using automatic capacitor banks, avoiding the need for a new
unit. An annual maintenance plan ensures ongoing performance.
Results
-
Improved power factor and increased production capacity
-
Avoided utility penalties
-
Reduced system stress and improved power quality
Testimonial
“The upgrade paid for itself almost immediately. Power Capacitors found a smart solution without
upselling us on unnecessary gear.” – Operations Director
Want to increase your site’s energy efficiency? Talk to our site services team about tailored solutions.
“We always use Power Capacitors Ltd. Nothing
is ever too much trouble, and the quality is second
to none!”
Operations Manager
AF Switchgear
AF Switchgear